Hong Kong International Airport

Apex Systems were hired to grind the 30000 metres of joint walls after the contractor had removed the failed expansion joint.

3 machines and 3 men were able to diamond grind the 30mm deep on both sides. Although the time frame was tight (10am-3pm) we were able to complete 2500 linear metres of joints per day.